If "Y" completes a particular work in 8 days, and "Z" in 24 days, how many days will it take if they work together?
  1. 6
  2. 4
  3. 2
  4. None of these
Explanation

Combined rate = 1/8 + 1/24 = 1/6.

Hence, time taken together = 6 days.